Project Description
This project will renovate the existing playground and picnic area for multi-purpose recreation and leisure uses while providing accessibility and stormwater management.
Background
The existing playground was installed in 1998. It will be removed, and a new playground will be installed in its place. Local Park playgrounds are typically 3,500 to 5,000 square feet in size and include playground equipment to meet the needs of children from ages 2-12, and seating for caregivers. Typical types of equipment include swings, play structures, and smaller freestanding pieces.
The new playground will have a shelter, a swing set, two zip lines, equipment for different age groups, and a seating area.
Status/Project Update
The old swings were removed, and replaced with a new biggo swing on the north side of the playground in 2022.
June 2025 Update: The playground construction is expected to last from spring to fall 2025.
Calendar and Meeting Notes
*Dates and times subject to change. Please contact the project manager for updates.
Dates | Notes and Project Resources |
---|---|
Fall 2021 | Community outreach |
Fall 2021 – Spring 2022 | Develop design concepts based on existing conditions assessment and community input |
Winter – Spring 2023 | Community review and comments. View survey results |
Winter – Spring 2024 | Finalize design and obtain permits |
Fall 2024 | Tennis court renovation completed |
Spring 2025 – Fall 2025 | Construction |