Project Description
The purpose of this project is to renovate existing park amenities. Renovated amenities include a basketball court, tennis court with hitting wall, three pickleball courts, seating areas adjacent to the courts, a nature play area, a new playground, a new picnic pavilion, site furnishings and stormwater management facilities. The parking lot will be configured to provide additional parking spaces. Additional new amenities may include a drinking fountain and a waterless toilet, dependent on available funding. Paths and trails to connect the amenities will also be renovated.
Background
Greenwood Local Park is located at 18700 Georgia Avenue in Olney. The park was developed in the 1970s and existing amenities include a playground, two tennis courts, a handball court, two full basketball courts, and a gazebo. The playground was last replaced in 1990 and the tennis and basketball courts were last renovated in 2001. A multipurpose field is located along the north side of the park and overlaps the school property. Paths located within the park do not meet current ADA accessibility guidelines.
Status/Project Update
The project is currently at the 100% design stage. The construction start date will be dependent upon receiving all final permit approvals and resolving land ownership issues with the Maryland State Highway Administration (SHA). A portion of land proposed for park redevelopment lies within the old Georgia Avenue right-of-way. SHA has determined that the land should be transferred to M-NCPPC ownership, which will affect the construction start date for this project. Parks will continue to provide updates to the project webpage as we obtain more information and is committed to moving forward with the park renovation project at Greenwood Local Park.
Project Timeline
*Dates and times subject to change.
Date | Project Stage and Resources |
---|---|
Winter 2022 | Virtual Community Meeting |
Winter/ Spring 2023 | Community meeting and survey results. Develop design concept based on existing conditions assessment and community input. |
Spring 2023 | Post concept for community review and comments |
Begin Summer 2023 | Finalize design and obtain permits |
Fall 2024 | 60% design concept posted |
TBD | Expected construction to begin |