Dalewood Drive Neighborhood Park

Existing playground located at Dalewood Drive Park

Project Description

This project will renovate Dalewood Drive Neighborhood Park, located between Brightview Street and Veirs Mill Road on Dalewood Drive in Wheaton. The park currently contains a small playground and lawn area. The project intends to renovate the existing park to improve the playground and accessibility and add a picnic seating area. 

Background

The approximately half-acre park is surrounded by single-family residential homes and a Verizon switching station to the west. The park is owned by Montgomery County and includes a large storm sewer right-of-way within its borders. The popular existing playground is accessed off Dalewood Drive.

Status/Project Update

The first community meeting took place on Tuesday, February 13, 2024, via Zoom. Montgomery Parks staff introduced the park renovation project, possible improvements, and two preliminary concepts. The community was asked to provide their feedback through Open Town Hall until March 13, 2024.

Revised Concept

The revised concept protects the existing Cherry tree by creating two playgrounds separated by a decked seating area under the existing tree. The existing tree will help provide shade to the new playground and seating area. A new maintenance access drive will be installed along the south side of the playground with a new curb cut on Dalewood Drive. (Click on image to enlarge.)

Updated concept of Dalewood Drive Park renovation featuring plantings, an updated playground, decking with seating and stormwater management.

Calendar and Meeting Notes

Dates are subject to change. Please contact the Project Manager for the most recent updates.

Project Date
Project Notes & Resources
Fall 2023Project start
 February 13, 2024
Virtual  Community Meeting #1
Watch the recording of the meeting
Vea la grabación de la reunión
February 13, 2024 – March 13, 2024Open Town Hall survey comment period
Spring 2024Develop park renovation concepts based on existing conditions assessment and community input
Fall 2025Revised concept plan
Fall 2025 – Fall 2026Finalize design and obtain permits
Summer 2027Anticipated start of construction, pending availability of funding

 

Last Updated: December 11, 2025