Maplewood-Alta Vista Park – Park Renovations

Areal rendering of Maplewood-Alta Vista Local Park renovation concept plan. The image shows where there will be sidewalk connections, a full basketball court and soccer court, a renovated tennis court, benches and sitting area, a renovated full basketball court with 4 hoops, play animal area, open area, resurfaced parking lot, stormwater facilities, drinking fountain, and portable toilet enclosure.

Project Description

This project proposes to renovate the western half of Maplewood-Alta Vista Park. The park is located on Alta Vista Road west of Rockville Pike in the Bethesda/Pooks Hill area of the County. The park features a variety of amenities including tennis and basketball courts, a playground, and a softball/soccer field overlay. An activity building is currently leased to a private entity. The intent of the project is to make infrastructure improvements to the park including: 

  • ADA accessibility improvements throughout the park
  • Stormwater management improvements throughout the park
  • Resurfaced basketball courts and tennis courts
  • Parking lot improvements to include two accessible parking spaces and an enclosure for porta-potties
  • Entrance driveway improvements including new sidewalk and curbs
  • One continuous accessible walkway will be provided between Alta Vista Road and Linden Avenue and connect to the parking lot, PAB building, the courts, the shelter, and the playground.
  • A new picnic shelter
  • A new drinking fountain
  • Lighting improvements with a new light and new accessible light switches
  • Landscape enhancements 

*Renovations to the athletic fields are excluded from this project. 

Background

The approximately 10.3-acre park is surrounded by single-family, residential housing to the east, south, and west, with high-density residential to the north. The eastern portion of the park consists of the athletic fields and expanses of open space with tree cover. An activity building in the central portion of the park is leased to a private entity. Other amenities in the park include a playground, basketball and tennis courts, and a parking lot.  

Project Timeline

*Dates and times subject to change.

DateProject Stage and Resources 
November 2023
December 2023
Solicit additional community input
January 16, 2024Virtual community meeting. View the recording

January 16 Community Meeting Presentation (accessible PDF)
January 16 – February 12, 2024Online survey open.
May 15, 2024In-person Community Meeting. Updated site plan posted
Summer 2024 – Winter 2026Finalize Park renovation design, and submission of design/construction documents for permitting
Spring 2027Construction bidding/procurement
Summer 2027Construction of park improvements starts
Last Updated: November 2, 2026