Project Overview
This project will improve the portion of Little Falls Stream Valley Park between Dorset Avenue and Norwood Park. The work includes renovating Little Falls Trail and naturalizing Willett Branch stream channel.
Existing Conditions and Proposed Improvements
Little Falls Trail
This project will improve approximately 0.5 miles of the Little Falls Trail between Dorset Avenue and Norwood Park in Bethesda. Improvements include repairing drainage issues, rehabilitating aging pavement and culverts, correcting pavement damage caused by tree roots, and improving trail accessibility to comply with Americans with Disabilities Act (ADA) standards.
The project will also improve existing trail connections to nearby neighborhood roads and sidewalks (Willett Parkway, Langdrum Lane, Drummond Avenue, and Cumberland Avenue) and add a new 6-foot-wide paved connection from the DeRussey Parkway cul-de-sac to Little Falls Trail. The trail between Langdrum Lane and Drummond Avenue will be rerouted to improve drainage. These upgrades will provide a safer, more accessible, and better-connected trail experience for visitors.
Willett Branch
This project will restore approximately 1,650 feet of Willett Branch and 175 feet of the Bethesda Pool Tributary by replacing an aging concrete channel with a more natural stream. The new stream design will include pools, rocky riffles, natural stone and wood features, and native trees and shrubs to improve habitat and stream health.
The project area extends from just downstream of the Capital Crescent Trail crossing to just upstream of the second crossing beneath Little Falls Parkway. Existing culverts under Little Falls Parkway will remain in place. These improvements will create a healthier, more resilient stream corridor while enhancing the surrounding natural environment.
Project Status
The project is in the 30% concept design phase. Current work includes site analysis, preliminary modeling, concept studies, and early 30% design ideas.
Project Funding
The trail renovation is jointly funded through the Trails: Hard Surface Renovation capital project and a Maryland Department of Natural Resources Local Parks and Playgrounds Infrastructure Initiative grant. The stream naturalization work is funded through Montgomery Parks Stream Protection capital improvement project.
Project Schedule and Community Meeting
Dates, events, and project milestones are anticipated and are subject to change.
| Date | Project Stage and Resources |
|---|---|
| Spring/Summer 2026 | Preliminary concept design, including project scoping, topographic survey, site analysis, concept studies, and preliminary modeling |
| Fall/Winter 2026 | 30% concept design |
| Spring 2027 | 60% design plans |
| Spring 2027 (anticipated) | Community meeting: date, time and location to be announced |
| Summer/Fall 2027 | 90% design plans |
| Winter 2028 | 100% construction plans and construction bidding |
| Spring 2028 – Winter 2029 | Construction |