This project renovates and replaces the existing playground in Newport Mills Local Park, located at 11201 Newport Mill Road, Wheaton, MD.
The existing playground will be removed and a completely new playground will be installed. Local park playgrounds are typically 3,500 to 5,000 square feet in size and include playground equipment to meet the needs of children from ages 2 to 12. Typical types of equipment include swings, play structures, and smaller freestanding pieces of equipment such as spring rockers or spinning elements.
Playground design was approved by the community. Construction documents are being prepared for a late winter/early spring installation.
New playground open Spring 2020. Old playground scheduled to be removed in Spring/ Summer 2020.
Links to review meeting notes and presentation materials will be attached to each applicable calendar event as it is scheduled and completed.
DATE/TIME |
DISCUSSION AND MEETING NOTES |
LOCATION |
Summer 2018 | Design with public review | |
Fall 2018 | Finalize design | |
Fall 2018/Winter 2019 | Development construction documents | |
Spring 2019 | Construction begins | |
Winter 2020 | Construction complete | |
New playground open. Old playground scheduled to be removed in Spring 2020. |
*Dates and times are subject to change.
Kathleen Dearstine, Project Manager
Kathy.Dearstine@MontgomeryParks.org
301-650-2883